Dreamlife Church switched to Infinite Energy as their grid electricity supplier and also commissioned IE to engineer, procure and construct a 40kW solar PV system complete with a real-time grid and solar monitoring solution.
Dreamlife Church made the decision to source a material portion of their electricity supply from a green and renewable energy source because it would not only help reduce their carbon footprint but mainly because they saw it as the best use of the Church’s funds. The solar PV system will pay for itself in a few years and the solar portion of their electricity bill will also be free.
Company | Dreamlife Church |
---|---|
Location | Wangara |
Installation Date | 07 / 2014 |
Industry | Community |
Solution | Solar Power & Grid Electricity - System capacity 39.78 kW
|
CO2- e. Abatement Per Year | 54 tonnes |
CO2 Equivalent Reduction | 202 trees saved per year |
Energy Output Per Year | 71,200 kWh |
Solar % of Consumption | 40% |
Grid Electricity % of Consumption | 60% |